Building Works Update

Works to be undertaken this week - 19th to 22nd December

 Installation of in-ground services to Coles building  Pad Footings to Coles Building  Core fill and backfilling blockwork retaining walls to loading dock area  Continuation of in-ground Stormwater Cell System  Ongoing demolition and strip out of Nextra area in preparation of Best & Less expansion and new Fire Passage works  Site clean-up and secure site for Christmas shutdown  Line marking and associated works for new Liquorland delivery bays and relocation of Taxi Bays The Development site will be shutdown from 3pm Thursday, 22 December 2016 and reopened Wednesday, 4 January 2017.