Building Works Update

Monday 30th January to Sunday 5th February 2017

Works to be undertaken this week: - Installation of in ground services & refrigeration to Coles building - High level services to Best & Less Stage 1 area - Continuation of cool room slabs - Commence concrete pours for Coles prep areas - Completion of new fire passage corridor Tuesday, 31 January 2017 - Hoarding alterations within mall to Nextra to accommodate fire corridor handover. - Demolition of redundant fire corridor - Casting of tilt panels to Coles building - Continuation of demolition to mall areas and redundant Liquorland stockroom. - Installation of Hoarding to Best& less Stage 2 - Commence Best & Less Fitout including back of house and office fitout.