Building Works Update

Building works to be undertaken at the centre the week ending 19th February 2017.

COLES

Installation of in ground services to Coles building //  Installation of in ground refrigeration to Coles building // Continuation of Cool room Slabs // Concrete Pours for Coles Prep Areas and BOH Slabs // FRP Columns to Coles Mezzanine Slab // Casting of Tilt Panels to Coles Building // Continuation of Demolition to Mall Areas and redundant Liquorland stockroom.

Installation of Tilt Panels **COMMENCE MONDAY, 20TH DUE TO WET WEATHER DELAYS.  CARPARK NEAR MCDONALDS IMPACTED**  Tilt panel lifting will take place Monday, 20th February 2017 from 5am.

The exclusion zone for the crane is marked up in red in relation to the development site fence which is blue. Perkins staff will be inside the exclusion zone to ensure no unauthorised access by the public during lifting.

BEST & LESS
 
Best & Less - Hoarding 1 Area:  
 
Services works // Floor preparation // Installation of ceiling and bulkheads // Glazing to shop front // Install POS Counter // Install lease line signage // Install bi fold door // Fit off ceiling services // Paint ceiling.
 
Best & Less - Hoarding 2 Area: 
 
Define temp BOH internal walls Rough in electrical services // Rough in hydraulic services.  **LANEWAY SHUT DOWN REQUIRED 20TH FEBRUARY 2017 – 7AM UNTIL 12PM MIDDAY**